Systemic-infrastructure-risk explainer ("Oh Shit" theme) — not tied to a live news event; full DOE/NERC report text fact-checked line-by-line before scripting
On what's here: the two primary reports (DOE's 2024 large-power-transformer
resilience report to Congress, NERC's 2025 Long-Term Reliability Assessment) were supplied to
production in full and checked claim-by-claim against the script before recording. One figure
(the 3-Schnabel-railcar fleet size) is trade-press-sourced rather than from either government
report — flagged below, not hidden.
DIRECT = confirmed against the primary report's own text.
TRADE = sourced from industry/trade reporting, not a primary government document.
Primary source — U.S. Department of Energy, 2024 LPT resilience report